Design, procurement and construction support for a new 32km 8″ pipeline from Hawthorne Energy’s Carstairs Gas Plant to AltaGas’ Harmattan Gas Plant.
– The new 8″ sour gas pipeline was required to replace an existing 10″ line that was failing due to excessive wall loss.
– Design of 6 new riser site stations and tie-ins at the Hawthorne Carstairs Gas Plant and the AltaGas Harmattan Gas Plant.
– Utilization of existing infrastructure and instrumentation at the gas plants and riser stations for cost savings.
– Upgrades to existing plant utility tie-ins to ensure safety and regulatory compliance.